Insurance Claim Approved Roof Replacement
Project Updates
09/25
Due to weather expected tomorrow, Thursday 09/22, work will not take place. Crews will return Friday 09/23, weather permitting. This shouldn't impact the overall schedule — we expect to move onto the next buildings Monday 09/26 as planned.
09/19
Today we will be beginning on buildings labeled 4, 5, and 6. Questions? Contact your management company or Stronghouse at (123) 456-7890 or
[email protected].
09/16
We are finishing up the first three buildings. Thanks everyone for your cooperation.
09/15
Today we will be delivering and lifting materials onto buildings numbered 4, 5, and 6.
09/12
We are officially beginning the project today! Starting on buildings labeled 1, 2, and 3. Questions? Contact Stronghouse at (123) 456-7890 or
[email protected].
09/10
Please refer to the building map for reference on which buildings will have materials delivered and boomed each week. Schedule is weather permitting.
Project Schedule
| Date |
Week |
Buildings |
| 09/10 | Week 1 | Buildings 1, 2 and 3 |
| 09/17 | Week 2 | Buildings 4, 5 and 6 |
| 09/24 | Week 3 | Buildings 7, 8 and 9 |
| 10/01 | Week 4 | Buildings 10, 11 and 12 |
| 10/08 | Week 5 | Buildings 13, 14 and 15 |
Project Information
Timing
Stronghouse will be assisting with insurance claim approved roof replacements throughout the community — all buildings.
We will have 3 crews onsite and estimate each building at approx. 5 days to complete. The entire project should wrap up in about 5 weeks, weather permitting.
Working hours: Mon.–Sat., 7:00am–dusk.
Vehicles
Very Important:
Have your vehicles off the driveway and moved away from your building by 7:00 AM on the day(s) your building is scheduled to prevent damage.
Suggestions for a Problem-Free Roof
- Remove patio furniture, grills, and property from decks/patios as well as fragile wall items — contractor is NOT liable for such damages.
- Remove all pet waste before project begins.
- Close window coverings during the day while work is underway.
- Notify us of any special or delicate plants/shrubs so we can protect them.
Clean Up
- Site cleaned during the day and at end of each day.
- Lawn swept with magnetic "nail-finder" to reduce leftover nails.
- Tools and materials kept neatly organized and out of the way.
Conditions Beyond Our Control
- Existing structural issues such as loose plaster, sagging rafters, nail-pops, or previously rotted materials.
- Scheduling delays due to weather or emergencies. We will do our best to minimize any disruption.
Landscaping
If there are any special or delicate plants or shrubs, please notify us before the job starts and we will protect them as best as possible.